The widening of Varthur Main Road (SH-35) between Varthur and Gunjur is now due in 2027. Karnataka Road Development Corporation Limited (KRDCL) is building it. It started as a 1.9 km widening and has grown to include a flyover near Varthur Kodi, with provision for a future double-decker structure and a metro alignment. Of the 198 properties notified for land acquisition, 19 were still pending in late 2025, which is what pushed the deadline. Meanwhile, a 70 km pothole-repair drive covering SH-35 stretches is under way, with one year of maintenance included.
This update explains what is being built, why it is late, and what it means for commuters and homebuyers along the Whitefield–Varthur–Sarjapur corridor.
SH-35 widening at a glance
| Item | Detail |
|---|---|
| Road | Varthur Main Road, State Highway 35 (Whitefield to Sarjapur) |
| Stretch | Varthur to Gunjur |
| Agency | Karnataka Road Development Corporation Limited (KRDCL) |
| Scope | Road widening, a flyover near Varthur Kodi, provision for a double-decker structure and a metro alignment |
| Land acquisition | 198 properties notified; 19 pending as of November 2025 |
| Expected completion | 2027 |
| Interim works | 70 km pothole repair drive with one-year maintenance |
Why it matters
SH-35 is the spine of East Bangalore’s southern belt. It links Whitefield and ITPL to Varthur, Gunjur and Sarjapur, and feeds traffic towards Marathahalli and the Outer Ring Road. The Varthur Kodi junction and the narrow Varthur–Gunjur stretch are its worst bottlenecks at peak hours. Widening them, with a flyover at Varthur Kodi, is the single biggest traffic fix planned for the area.
Why it is late
- Land acquisition: a handful of the 198 properties needed were still unresolved in late 2025.
- Scope growth: adding the flyover and provisions for a future double-decker and metro widened the design.
- Progress: TDR (transferable development rights) issued through the Greater Bengaluru Authority has helped clear several plots, and work pace has improved.
Road deadlines in Bangalore often slip, so buyers should treat 2027 as the target rather than a guarantee.
What it means for homebuyers
- Short term: expect construction and diversions on the Varthur–Gunjur stretch through 2027.
- Long term: once complete, travel between Varthur, Gunjur and Sarjapur Road should be quicker, and the corridor’s homes will be better connected.
- Price effect: completed road upgrades usually lift prices along the corridor, so buying before completion captures that gain.
- Location within the corridor: homes closer to Whitefield and ITPL depend less on the Varthur–Gunjur stretch.
Prestige Rosewood and SH-35
Prestige Rosewood is on Varthur Main Road, opposite Varthur Lake, on the Whitefield side of Varthur Kodi:
- Distances: ITPL is 4 km (12 minutes), Hopefarm Channasandra metro 4 km and Marathahalli 6 km, so most daily commutes don’t use the Varthur–Gunjur stretch.
- The upgrade: the SH-35 works will improve its link south to Sarjapur Road, 12 km away.
- Timing: Rosewood’s possession in December 2030 comes after the road’s 2027 target.
See the Varthur Road guide, Sarjapur and Marathahalli distances and metro connectivity.
Varthur Road widening: questions answered
When will Varthur Road widening be completed?
The Varthur–Gunjur stretch of SH-35 is now expected to be completed in 2027, according to KRDCL.
Who is building the Varthur Road widening?
Karnataka Road Development Corporation Limited (KRDCL).
Why is the Varthur–Gunjur road delayed?
Land acquisition for a small number of the 198 notified properties was still pending in late 2025, and the scope grew to include a flyover near Varthur Kodi and provisions for future structures.
Will there be a flyover at Varthur Kodi?
Yes. The expanded SH-35 project includes a short flyover near Varthur Kodi junction.
Does the road work affect Prestige Rosewood?
Prestige Rosewood is on the Whitefield side of Varthur Kodi, 4 km from ITPL and the metro, so daily commutes to Whitefield don’t depend on the Varthur–Gunjur stretch. The upgrade will improve its link to Sarjapur Road before Rosewood’s possession in December 2030.
Status as reported by KRDCL and Bengaluru media up to late 2025; timelines can change.
More Varthur guides: Varthur area guide · Varthur pin code · Varthur Lake · property rates · new projects · SH-35 widening · Gunjur and Balagere · all Varthur guides
Photo: Varthur road, Bangalore (13945201583).jpg by Ramesh NG from Bangalore, INDIA, CC BY-SA 2.0, via Wikimedia Commons.
Interested in Prestige Rosewood Phase 3?
Ultra-luxury 2, 3 & 4 BHK residences directly opposite Varthur Lake. Pre-launch from ₹1.75 Cr. Possession December 2030.
Request Price & Floor Plans →